Huddersfield Rail Upgrade Works Completed, Paving Way for Faster Services

Engineers have finished a 16-day programme of significant upgrades at Huddersfield and Deighton stations, enhancing reliability and capacity.

Close-up of railway tracks and ballast with overhead line equipment masts in the background.
AI

Close-up of railway tracks and ballast with overhead line equipment masts in the background.

Significant improvement works by the Transpennine Route Upgrade (TRU) in Huddersfield have been completed, bringing faster, more frequent, and reliable rail services closer for passengers across the North.

The 16-day programme of upgrades, which took place between Saturday 19 September and Sunday 4 October, saw engineers complete a series of major enhancements across the railway and at both Huddersfield and Deighton stations.
Key achievements include the installation of over 2km of new track through the Huddersfield area, supporting future capacity improvements and enabling faster services to overtake stopping trains. Additionally, more than 1.3km of track renewals and over 900m of drainage renewals were completed to improve service reliability.
Huddersfield station has seen significant progress, with platform extensions, restoration of the historic roof canopy, and subway extensions. Deighton station also received major upgrades, including platform extensions and the installation of a new accessible footbridge, which will feature lifts upon completion.
Further work involved installing over 50 overhead line equipment masts and steel structures for future railway electrification. Preparation works at A62 Leeds Road bridge are also underway ahead of its reconstruction to accommodate electrification, alongside signalling installations to enhance railway performance.
“

"Completing this latest phase of work is down to the dedication, skill, and teamwork of our teams. From infrastructure delivery to planning and keeping passengers on the move during the disruption to their journeys, every part of the programme has played a role in this latest work."

James Richardson · TRU Managing Director
“

"The work that has been completed over the last 16 days in the Huddersfield area is another crucial step towards delivering the benefits that the Transpennine Route Upgrade will bring for customers across the North. We have worked closely with our industry partners to keep customers on the move as these works have continued and we would like to thank our customers and local communities for their patience and cooperation whilst these improvement works have been taking place."

Liam O’Shaughnessy · TRU Programme Delivery Lead for Northern
Following this successful programme, attention will now shift to the next phase, which includes a 38-day closure of Huddersfield station from Thursday 24 December 2026 until Sunday 31 January 2027, for further transformative upgrades.
These upgrades are part of the wider multi-billion-pound TRU programme, aimed at transforming the railway between Manchester, Huddersfield, Leeds and York by improving capacity, reliability, and accessibility, while supporting the introduction of electric trains.
Additional weekend closures at Huddersfield station are scheduled for 10-11 October, 14-15 November, 13 December, and 20 December 2026, to complete the main station upgrades by early 2027.